The Lousiana Department of Transportation and Development will begin a $1 million project to modify the east and westbound exit ramps on I-10 at Ambassador Caffery on January 19, 2015. Most of the work will take place during the day, but crews will begin removing striping and re-striping the existing lanes from 7 PM until 6 AM tonight. You should expect intermittent lane closures over the duration of the project. This project is estimated for completion in March 2015. Motorists can expect some delays while the project is underway. DOTD apologizes for any inconvenience and reminds motorists to drive safely and be on the lookout for construction crews and their equipment.